Qantas today confirmed that the delivery of its first A380 would be delayed by six months as a result of manufacturing issues at Airbus.

The Chief Executive Officer of Qantas, Mr Geoff Dixon, said the airline was now scheduled to take delivery of the first of its 12 new A380 aircraft in April 2007.

"This is disappointing, given that we have met all of Airbus' deadlines for Qantas specifications, however we are developing contingency plans to ensure there is no impact on our schedules or available capacity during the six month delay."

Mr Dixon said possible contingencies under discussion included deferring the retirement of a number of aircraft, redirecting capacity, and bringing forward the delivery of other aircraft on order.

Mr Dixon said that all airlines with early A380 orders were in the same situation, and that Airbus had advised that the deliveries would be made in the same sequence with the same time differentials.

"We will be working closely with Airbus to ensure the new deadline is met," Mr Dixon said.

He said Qantas would also be seeking compensation from Airbus in line with the terms of its contract.

Issued by Qantas Corporate Communication (3276)